Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Iterative Tasks such as bi-weekly Project Meetings 1

Status
Not open for further replies.

sanmati

Computer
Sep 16, 2004
4
US
Hi

How do we define an Iterative Task e.g. biweekly Meetings? in MS Project ?
Thanks
 
Replies continue below

Recommended for you

Other than the Insert Recurring Task on the menu?

TTFN
 
Hi All,
I have assigned Work hrs to the Sub-tasks; It adds up as the Work Hours for the Parent Task (e.g. Meetings)
When I assign Resources to the Iterative Task, it messes up the Total Work hrs for the Parent;

I am doing anything wrong while assigning the resources for the Meeting?

Thanks
 
Seems to work OK for me. How are you assigning the resources?

TTFN
 
Hi
I got it; Now I am using "Customize Assignment" Screen ;
If the Weekly meeting lasts one hr,
I am entering as follows for each Meeting1 , Meeting 2 :
Task Type = Fixed Work

Resource % Work

Name1 100 1 h
Name2 100 1 h

It is OK now
Thanks
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top