i changed that, but it's still moving...for example...the activity had to start in 15.10.2006(and not started yet), and today is 15.11.2006, i do the schedule, but the activity is moved, and start date is now schedule data date...i want to planned activitys dates stay at place...how to do...
thx, i'll see, but always when i do F9 the duration is changed...i guess i can ask u more things(one more), i put the start date for the sam example, and the activity hasn't started yet, but i want to stay there, and i do schedule and the start date is now schedule data date
Q:How to activity...
yest they have, example, start date 1.09.2006, duration 30 days(end date 30.09.2006), i do schedule at the date 10.09.2006, and duration is now 40 days
When i do F9(schedule), my activitis durations are moved (they are longer) for the number of days from the last scheduling.Why is that?I have no resourses assign to the activities...