I know, and I'v tried this.
But when Project is calculating man-hours it still uses 7,5h, even if the workhoures in the calendar is from 07:30 - 19:30 (w/ breaks in between).
Therefore I guess it uses the "hours per day" in Tools -> Alternatives -> Calendar to calculate workhours.
But is this...
I'm managing a project with two groups of workers.
The first group is working 37,5h a week.
The second group is working 62,5h a week.
I can't seem to find a way to solve this without using the units-field. (E.g. A standard week = 62,5h. 0,6 units equals 1 man)
That way is not an option for...