I'm managing a project with two groups of workers.
The first group is working 37,5h a week.
The second group is working 62,5h a week.
I can't seem to find a way to solve this without using the units-field. (E.g. A standard week = 62,5h. 0,6 units equals 1 man)
That way is not an option for this project, because the unit(men) are in several groups of 8-12 people in MS Project, and would make it very difficult to keep track of how many people I actually need.
Any tips or tricks?
(It's difficult to explane this in english,
so just ask if you don's understand what I mean!)
The first group is working 37,5h a week.
The second group is working 62,5h a week.
I can't seem to find a way to solve this without using the units-field. (E.g. A standard week = 62,5h. 0,6 units equals 1 man)
That way is not an option for this project, because the unit(men) are in several groups of 8-12 people in MS Project, and would make it very difficult to keep track of how many people I actually need.
Any tips or tricks?
(It's difficult to explane this in english,
so just ask if you don's understand what I mean!)