Hi Gents / Lady's,
I am looking for Valve Pressure Test Centre and I cam across Dory Machinery in China.
www.valvetester.com
I would like to know if anyone has one or used one of their Machines and your thoughts.
Yeah I am in the same boat as you are.
We are getting requirements from clients to Torque Test Pneumatic DA & SR as well as Electrics. I had a look at Ventil unit but they are after 150k euro for one.
How long have you been in the company and in this position?
I have been at the company 12 months.
"Its easier to apologize after the fact than it is to get permission beforehand" - Haha on of my favorite saying. I am implementing as much as I can with my current level of authority, how ever I...
I am looking for some advice from people that have maybe dealt with a similar situation.
I work for a Major Global Company. My Job is to develop/manage an engineering department and a workshop.
Over the last 8 month I have had countless meeting with my GM & Regional VP and prepared...
Hi Gents / Ladies,
I have setup an assembly workshop in the back corner of our warehouse. We will be moving premises within 12 months but I would like to Partition it off from the rest of the warehouse mainly for O&HS reasons.
I looked to at temporary fencing with shade cloth, but it will not...
Having a step by step design log or proof of design is good. You will sometimes also find alternative designs paths that you might have overlooked. Its not a common practice. Few of my customer require a proof of design.
I work in valve instrumentation and control for oil/gas and I did a design...
Is there a way in MS Project to Highlight a Successor only after the Predecessor is 100% Complete(FS Connection)? To give a visual on the gantt chart that it can be commenced.
Also is there a way to prevent marking successor complete before the predecessor assuming FS Connection?
Looking at...
@Kenat
"Sometimes they seem to be the folk with slightly weaker technical skills that see moving into a management role as being their path to success."
So true. Thats why I left my last job.
@ ntweisen
Thanks for your thought. But I cant download what you posted as I am required to enter either my mobile number which then will automatically goes on a subscription plan of some sort. Not sure if this is against Posting Policies.
If you would like to help please attach excel files on...
Yeah I had a talk to my It Manager about using our existing oracle system but that will just be a nightmare for him. Plus it seems that we will be switching from oracle in a few years so its not worth the time to configure it for this.
Any other suggestions please.
Hi Gents and Ladies.
I am looking for some advice.
I am going to be Managing an Instrumentation and Control Center for my company here in Dubai. The budget has been approved and now its time to get everything planed and have it running smoothly.
From a management point of view I would like to...