That would be a hydro-pneumatic tank. What is the max gpm and pressure needed for the system, or what size pumps do you have?
The maximum VFD pump rate will be 1,395 gpm. The average will be a lot lower.
The pressure needed is about 75 psi.
It would be pumping straight from the clear well of a new small treatment plant. This development will be spread out and have their own treatment plant.
It will be for a development that wants no tanks.
I am just looking for some documents on lessons learned, typical design procedure, etc.
We are having a tank repainted. Our specs call for sandblasting in the morning and priming in the afternoon no more than 40 hours later.
We have a contractor screaming that they can sandblast for 2 days without priming and are asking for a variance and the ability to sandblast during the...
Does anyone know the reputation of this brand? We are considering them for a new sewage pump station.
However, I have never used them? Do they have a good reputation?
Hi,
We have a high flashing spring source that is under the influence of surface water. The turbidity is usually 1 to 5 NTU. However, it can flash readily during rain events to 100 to 150 NTUs. We were thinking about utilizing a Superpulsator sludge blanket type clarifier upstream of...
natural gas pipeline work. I am interested in transitioning to natural gas pipeline work.
Does anyone know anyone who has made this transition. Do you have any advice on this transition?
pipeline engineering.
Does anyone have any advice on how to make this trasition??
What about transitioning to petroleum pipeline engineering?
Do you know anyone how has made this transition???