We are trying to determine lighting requirement for a small process building. Is there a quick way to help determine wattage requirement per square footage? What about celling height? Thanks!
We have a situation where we have to route MV (4160v) cable in a LV duct Bank. Routing will involve Man Holes where LV and MV will be exiting PVC conduits and entering others as they head to their destination. MV cables are all shielded, with shields grounded on both sides. My question is, when...
I'm planning to add motor loads to an MCC fed from a 4160v swicthgear. For that, I'd like to to run a load flow and short circuit analysis to see if existing system can handle it. Both existing swicthgear and MCC have existing motor loads on them. My question is, if the plant gives me short...
LionelHutz, the Transformer example you've indicated is applicable here. The situation I have is simillar to 3 single phase transformers, each with 120v to neutral, and all connected in a Y configuration. The 1581VA load is across phases A and C, so the voltage across the load is 208v. This...
I'm configuring a 4 wire 120/208v panel and have this question. I have a 1581VA load, that I'd like to supply with a 2-pole 208v supply (Vac). I understand that a current of 7.6A would be seen by phases A and C. What does that mean VA wise to each phase? In other words, would each phase's load...
Electrical system study with all loads connected showed we need to modify primary Taps to -5% to maintain voltage. Currently, most of the loads are not connected, and bus voltages at MV level is around 4300v. If Taps are changed now, voltages might get over 4500v, which is high. First, would a...
Good point 7anoter4. dpc, do you know which NEC requirement is applicable with this? 250.122 talks about using the upstream overcurrent protector as guidance, but this is not present here.
I'm feeding a 1200A MV breaker directly from the secondary side of a 69K/4.16K transformer. I'm using 6 1/C #500 MCM (2 conductors per phase). Table 250.122 in NEC-2011 indicates a ground size of 3/0 if overcurrent device protecting cables is 1200A. In this case, there is no overcurrent device...
Thanks guys! Basler replacement relays are good options. Is there an advantage of using new relays, instead of just adding an external time delay elements (other than much more features maybe)?
I have a feeder with CO-9 relay I'd like to coordinate with downstream breakers. The time delay element is adjustable, but the instantaneous element (IIT) is the problem. Does anyone know if we can add a timer to the IIT element? How is that done?
All Panels, Tray, and Switchgear are in the same room, and connected to the same ground ring. The switchgear bus is connected to the ground ring by a large 500 MCM cable, so the ground ring will be the effective ground path back to the source panel. Would that be sufficient?
I have a switchgear cubical with a ground bus. The case is all grounded through the ground bar. The bar is connected to a local ground, and the 4160v feeder ground. We have multiple power circuits terminating in the switchgear, 120VAC, and 125DC. Do I have to pull a ground cable and terminate it...