gokulkrish2
Electrical
- Jun 29, 2008
- 79
Hello Everyone,
Hope everybody is doing great in this forum.
I am right now working on a commissiong of a 15MW steam turbine generator and have some questions for you guys to answer
I represent the customer who bought the generator unit.
While we were commissioning this generator two weeks before, we had an incident where the coupling broke due to wrong synchronization(or atleast we think-investigation still going on). But the project is proceeding and we have shipped the generator to the factory to check its integrity
I am schedule to go to the factory to inspect and monitor the testing process and report back to the customer.
Do you guys have some checklist where i should be focusing and looking for damages in the generator. This is the first time i am going to the generator factory.
BACKGROUND.
The generator was almost commissioned and was synchronized to the utility.
The night before the incident the generator was set to output 10MW and it ran for the whole night
The next morning we were going to check an EStop circuit and Auto synchronization function
So, we had to trip the unit and so we gradually reduced the output of the generator
We brought it to 500KW and ready to trip
But the Hyndai representative wanted to do some final point to point checks on the wiring diagrams
We they were doing this we heard sudden noise and the next thing we know, the coupling at the Turbine-Gear box end was broke.
The emergency lube oil circuit was broke and oil was splattered all over the place
But the Turbine and the generator rotate atleast for 3 minutes after the coupling broke. The vibration monitors did go to the alarm stage but never to a trip level state.
When we questioned the Turbine and Generator representative, they would not give us any answer as they claim the investigation is going on and they wont be able to issue a statement until their underwriters are given one
We questioned the Electrical Technician who helped the Hyundai Generator Engineer and he claims that the Hyndai guy had him bypass the sync check relay.
Now i have two questions:
What do you guys think would have happened here.
What would be the worst case damage to expect. When i got the inpsect the factory testing what should i focus on? What could have gone wrong as far as the generator is concerned- Shaft? End winding? rotor? Stator?
I would appreciate any insights and advice i can get from experts like you people.
Thanks
gokul
Hope everybody is doing great in this forum.
I am right now working on a commissiong of a 15MW steam turbine generator and have some questions for you guys to answer
I represent the customer who bought the generator unit.
While we were commissioning this generator two weeks before, we had an incident where the coupling broke due to wrong synchronization(or atleast we think-investigation still going on). But the project is proceeding and we have shipped the generator to the factory to check its integrity
I am schedule to go to the factory to inspect and monitor the testing process and report back to the customer.
Do you guys have some checklist where i should be focusing and looking for damages in the generator. This is the first time i am going to the generator factory.
BACKGROUND.
The generator was almost commissioned and was synchronized to the utility.
The night before the incident the generator was set to output 10MW and it ran for the whole night
The next morning we were going to check an EStop circuit and Auto synchronization function
So, we had to trip the unit and so we gradually reduced the output of the generator
We brought it to 500KW and ready to trip
But the Hyndai representative wanted to do some final point to point checks on the wiring diagrams
We they were doing this we heard sudden noise and the next thing we know, the coupling at the Turbine-Gear box end was broke.
The emergency lube oil circuit was broke and oil was splattered all over the place
But the Turbine and the generator rotate atleast for 3 minutes after the coupling broke. The vibration monitors did go to the alarm stage but never to a trip level state.
When we questioned the Turbine and Generator representative, they would not give us any answer as they claim the investigation is going on and they wont be able to issue a statement until their underwriters are given one
We questioned the Electrical Technician who helped the Hyundai Generator Engineer and he claims that the Hyndai guy had him bypass the sync check relay.
Now i have two questions:
What do you guys think would have happened here.
What would be the worst case damage to expect. When i got the inpsect the factory testing what should i focus on? What could have gone wrong as far as the generator is concerned- Shaft? End winding? rotor? Stator?
I would appreciate any insights and advice i can get from experts like you people.
Thanks
gokul