PRENG
Structural
- Apr 1, 2002
- 3
Greetings all,
I am designing my first concrete tank and had a few questions. The tank is (3) 36' sq. chambers in a line, sharing walls. It is a total of 23' tall (plus the slab depth), is burried 20', and does not have a top. The water table is 11' below the top of the tank.
I have completed the slab design using RISA 3D and compression only springs, by the way JAE's 9-18-2000 suggestion to use upper and lower bound soil constants to envelope the solution has already helped me. (I don't have soil info...yet). FYI the slab required had a d=23". Which seems thick to me but is helping me with the bouyancy problem anyway.
Now I am ready to start the wall design/detailing. Here are my thoughts, I'd appreciate any comments:
1. The walls could be designed as a cantilever (conservitive), by using PCA's "Rectangular Concrete Tanks" publication moment/shear coefficents, or by FE analysis. I'm leaning to designing as a cantiliver. How have you performed this design? How ever performed, I will consider the different loadings, backfilled/not backfilled, empty/full chamber.
2. Waterstops will be required at the joints. I am concerned about their placement in relation to the joint reinforcement. If the reinf. has say 2" cover I am not going to be able to fit the WS between the bar and the inside of the tank. On the other hand if I put the WS more toward the center of the wall the fluid will be able to reach the unprotected reinf. It will even get worse at the divider walls (on either side of the middle cell) where they meet the perimeter wall and the slab. Any experience with standard construction/design would be greatly appreciated.
3. Lastly, thanks for you patience, I intend to design the corner reinforcement to restrain the wall's end reaction, is that correct? I will probably end up having hooks for each mat of horizontal wall reinforcement.
Thanks in advance
JT
I am designing my first concrete tank and had a few questions. The tank is (3) 36' sq. chambers in a line, sharing walls. It is a total of 23' tall (plus the slab depth), is burried 20', and does not have a top. The water table is 11' below the top of the tank.
I have completed the slab design using RISA 3D and compression only springs, by the way JAE's 9-18-2000 suggestion to use upper and lower bound soil constants to envelope the solution has already helped me. (I don't have soil info...yet). FYI the slab required had a d=23". Which seems thick to me but is helping me with the bouyancy problem anyway.
Now I am ready to start the wall design/detailing. Here are my thoughts, I'd appreciate any comments:
1. The walls could be designed as a cantilever (conservitive), by using PCA's "Rectangular Concrete Tanks" publication moment/shear coefficents, or by FE analysis. I'm leaning to designing as a cantiliver. How have you performed this design? How ever performed, I will consider the different loadings, backfilled/not backfilled, empty/full chamber.
2. Waterstops will be required at the joints. I am concerned about their placement in relation to the joint reinforcement. If the reinf. has say 2" cover I am not going to be able to fit the WS between the bar and the inside of the tank. On the other hand if I put the WS more toward the center of the wall the fluid will be able to reach the unprotected reinf. It will even get worse at the divider walls (on either side of the middle cell) where they meet the perimeter wall and the slab. Any experience with standard construction/design would be greatly appreciated.
3. Lastly, thanks for you patience, I intend to design the corner reinforcement to restrain the wall's end reaction, is that correct? I will probably end up having hooks for each mat of horizontal wall reinforcement.
Thanks in advance
JT