I am working on a project in a remote location. The project is a reinforced concrete box culvert storm drain. The only concrete plant in the area is a 90 minute drive away plus another 10 - 30 minutes waiting to unload so that readymix will be 2 hours total in the mixer. The producer says they have suitable mixes with retarder added that can go that long and meet state DOT specs.
1)should I believe them and
2)anything special I should do in plans / specs / QC to make sure the finished concrete comes out ok?