SteelPE
Structural
- Mar 9, 2006
- 2,759
I am working on a project where we have some interior not bearing masonry walls and an elevator shaft out of masonry. A GC was brought in to run the project and help the design team during the planning phase to help with budgeting the project. Somewhere behind my back a decision was made to switch these walls to 6" CMU. Now I'm not worried about the non load bearing walls but I am a little worried about the masonry shaft walls for the elevator. Are these blocks the same as the 8" blocks? Meaning:
I can get vertical reinforcing into them
We can obtain joint reinforcing (ladur reinforcing)
I can get bond beams into the walls
Keeping with masonry construction the dimension of the block would be 5 5/8" thick
In 17 years I have never been asked to use 6" CMU (maybe I am just sheltered here).
The issue is that all of the architectural drawings were switched to 6" CMU and the interior of the building is tight so a switch back is going to be meet the wrath of everyone above.
I can get vertical reinforcing into them
We can obtain joint reinforcing (ladur reinforcing)
I can get bond beams into the walls
Keeping with masonry construction the dimension of the block would be 5 5/8" thick
In 17 years I have never been asked to use 6" CMU (maybe I am just sheltered here).
The issue is that all of the architectural drawings were switched to 6" CMU and the interior of the building is tight so a switch back is going to be meet the wrath of everyone above.