saadeh
Structural
- Apr 30, 2014
- 6
Dear fellow bridge engineers,
I'm currently working on a local bridge project which employs precast, post-tensioned girders, and the other day I had an argument with the consultant and my prestressing sub-contractor (Dywidag) about the permissible stresses in stressing strands and it turned out that we might have a problem with about 25 girders regarding the maximum allowable stresses in tendons, my subcontractor field engineer have a poor technical knowledge and so does the consultant !
before jacking, the sub-contractor provides us with his field calculations regarding jacking force, losses, theoretical elongation,...etc.
and for no good reason, I used to forward these calculations to the consultant for approval without reviewing it myself. A wihle ago, we had a problem with one of the girders and due to some site problems, we had to use 14 strands in one of the tendons instead of 15, when we discussed this issue with the consultant, he immediately replied that there's no problem and we can go on and start jacking, later when I asked for a written letter to secure our act of using 14 strands instead of 15 based on our discussion with him, he changed his mind completely and refused to accept the completed girder and told us that the designer checked the girder and the maximum allowable stresses in the tendons are exceeded !!
Now, I'm doing a check on the stresses and going over a redesign of the girder, but I came across section 5.9.3 where it states that the maximum stresses allowed in tendons at anchorage and couplers immediately after anchor set is 0.7Fpu....
My question is, does this mean that the stresses after the instantaneous losses (friction, seating, and elastic shortening)shall not exceed the given limit ? my subcontractor told me that you have only to consider seating losses only when doing this check without taking into account the friction and shortening !! I don't understand why to consider only seating when and at the same time the other two loss types take place !! my local code of practice is a translated version of AASHTO LRFD specifications and the translation is very poor and this check is not clear to me, in the same time the English version states that this check is done (AFTER ANCHOR SET) and my subcontractor understood it literally, but as per my understanding, it should include all instantaneous losses.... I have a copy of Edward Nawy's Prestressed Concrete and it states that this check is done after transfer (which means after all instantaneous losses) so I need another interpretation for this sentence from a prestressed expert
and as I said earlier, my subcontractor has poor knowledge..
Another issue, I have three tendons and each tendon is jacked separately, the strands of each tendon are jacked all together, but tendons are jacked separately one after the other, so doesn't this impose elastic shortening losses ?? again, my sub-contractor says no!!
Please Help! and thanks in advance...
I'm currently working on a local bridge project which employs precast, post-tensioned girders, and the other day I had an argument with the consultant and my prestressing sub-contractor (Dywidag) about the permissible stresses in stressing strands and it turned out that we might have a problem with about 25 girders regarding the maximum allowable stresses in tendons, my subcontractor field engineer have a poor technical knowledge and so does the consultant !
before jacking, the sub-contractor provides us with his field calculations regarding jacking force, losses, theoretical elongation,...etc.
and for no good reason, I used to forward these calculations to the consultant for approval without reviewing it myself. A wihle ago, we had a problem with one of the girders and due to some site problems, we had to use 14 strands in one of the tendons instead of 15, when we discussed this issue with the consultant, he immediately replied that there's no problem and we can go on and start jacking, later when I asked for a written letter to secure our act of using 14 strands instead of 15 based on our discussion with him, he changed his mind completely and refused to accept the completed girder and told us that the designer checked the girder and the maximum allowable stresses in the tendons are exceeded !!
Now, I'm doing a check on the stresses and going over a redesign of the girder, but I came across section 5.9.3 where it states that the maximum stresses allowed in tendons at anchorage and couplers immediately after anchor set is 0.7Fpu....
My question is, does this mean that the stresses after the instantaneous losses (friction, seating, and elastic shortening)shall not exceed the given limit ? my subcontractor told me that you have only to consider seating losses only when doing this check without taking into account the friction and shortening !! I don't understand why to consider only seating when and at the same time the other two loss types take place !! my local code of practice is a translated version of AASHTO LRFD specifications and the translation is very poor and this check is not clear to me, in the same time the English version states that this check is done (AFTER ANCHOR SET) and my subcontractor understood it literally, but as per my understanding, it should include all instantaneous losses.... I have a copy of Edward Nawy's Prestressed Concrete and it states that this check is done after transfer (which means after all instantaneous losses) so I need another interpretation for this sentence from a prestressed expert
Another issue, I have three tendons and each tendon is jacked separately, the strands of each tendon are jacked all together, but tendons are jacked separately one after the other, so doesn't this impose elastic shortening losses ?? again, my sub-contractor says no!!
Please Help! and thanks in advance...