MALKOBANI

Structural
Oct 16, 2006
21
0
0
Hi all

I am designing a concrete building that will have a future storey. I want to account for future splicing rebars. Can you advise me on the best way of doing this.

Thanks for your input.
 
Replies continue below

Recommended for you

Use rebar couplers (such as Lenton) with internal threads - set flush with the top of the column stubs. The threaded openings can be plugged with plastic caps and the whole column stub covered with roofing.

 