RBCSCI
Aerospace
- Jul 24, 2019
- 4
I have a very small volume, high complexity, long cycle time product. A typical build takes roughly 6 months. There are test points in the build process with low yields and long rework cycles. I'm trying to account for those failures/reworks in my production plan. Here is my current approach:
Test Point 1 - 50% yield with a 14 week rework cycle
Test Point 2 - 80% yield with a 20 week rework cycle
My approach is to incorporate an extra 7 weeks of cycle time (.5 x 14) following Test Point 1 and 4 weeks of cycle time (.2 x 20) following Test Point 2 into the standard cycle time for each unit. I expect that I will end up with some units ahead and some behind, but the aggregate should stay close to nominal.
My alternate approach might be to build back-up units in parallel, which could be used as line fill for failures, but my unit cost is $200K each. That seems cost prohibitive.
I'm looking for ideas on how to maintain a stable production schedule that won't have my customer panicking every couple weeks.
Thanks!
Test Point 1 - 50% yield with a 14 week rework cycle
Test Point 2 - 80% yield with a 20 week rework cycle
My approach is to incorporate an extra 7 weeks of cycle time (.5 x 14) following Test Point 1 and 4 weeks of cycle time (.2 x 20) following Test Point 2 into the standard cycle time for each unit. I expect that I will end up with some units ahead and some behind, but the aggregate should stay close to nominal.
My alternate approach might be to build back-up units in parallel, which could be used as line fill for failures, but my unit cost is $200K each. That seems cost prohibitive.
I'm looking for ideas on how to maintain a stable production schedule that won't have my customer panicking every couple weeks.
Thanks!