Eng_Struct
Structural
- Sep 23, 2022
- 57
Hi All,
I have an existing concrete floor beam that is designed for a certain floor live load. However, the client is installing a piece of equipment that will result in an area load larger than the design floor load. There is no information available on the reinforcing of the beam.
I am considering installing a steel beam directly below the concrete beam (supported by columns at each end with post-installed wall plates)to support the additional load from the equipment. The rationale is that the existing concrete beam will continue supporting the dead load and once it starts deflecting even a nominal amount due to the live load, it will engage the steel beam below that will provide the support for additional loading.
Is it correct to design the steel beam to take additional live based on the above rationale? Note that the conservative approach will be consider that the concrete beam fails and all the load (including both dead and new live) is supported by the steel beam. However, this approach causes issues with the floor slab as the steel beam will not be stiff enough and the two-way slab will start getting more deflection.
Regards
I have an existing concrete floor beam that is designed for a certain floor live load. However, the client is installing a piece of equipment that will result in an area load larger than the design floor load. There is no information available on the reinforcing of the beam.
I am considering installing a steel beam directly below the concrete beam (supported by columns at each end with post-installed wall plates)to support the additional load from the equipment. The rationale is that the existing concrete beam will continue supporting the dead load and once it starts deflecting even a nominal amount due to the live load, it will engage the steel beam below that will provide the support for additional loading.
Is it correct to design the steel beam to take additional live based on the above rationale? Note that the conservative approach will be consider that the concrete beam fails and all the load (including both dead and new live) is supported by the steel beam. However, this approach causes issues with the floor slab as the steel beam will not be stiff enough and the two-way slab will start getting more deflection.
Regards