Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Addition of PWHT

Status
Not open for further replies.

Hansac

Mechanical
Dec 6, 2006
40
Hi.

Scenario: A pressure vessel has four WPS/PQR. Three have PWHT, the 4th WPS/PQR does not have PWHT. All are valid WPS/PQR. After completion of welding, the whole pressure vessel goes into a furnace for heat treatment.

Question: Is this an NCR? Does the 4th WPS have to be requalified in order to rectify as per ASME IX?

Your responses are very much appreciated.
 
Replies continue below

Recommended for you

Could the one w/o PWHT be used for structural welding (skirt, legs) after PWHT. Ask the Manufacturer to provide a weld map. If the weld was used for pressure parts subject to PWHT, you have an NCR.
 

IS this a NCR?
YES, As you are applying an PWHT on an non-PWHT PQR this is against ASME Sec IX QW-407.1 irrespective of the Building Code this is a clear violation.

Does the 4th WPS have to be requalified in order to rectify as per ASME IX?
YES, ASME Sec IX QW-407.1 is an essential parameter. so to change from Non-PWHT to PWHT you need to Qualify a new PQR. since PWHT is to be done and it is a essential variable. so technically it will be new PQR.

@weldstan i do not think being a structural or pressure weld will play a part in it.

 
I have reviewed well over 10,000 WPSs and generated nearly the same per ASME and AWS Codes and yes WPS's have been issued for structural items w/o PWHT for pressure items subject to PWHT when those items were welded after PWHT. I've also rejected numerous WPSs w/o PWHT which were intended for items subject to PWHT.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor