Hansac
Mechanical
- Dec 6, 2006
- 40
Hi.
Scenario: A pressure vessel has four WPS/PQR. Three have PWHT, the 4th WPS/PQR does not have PWHT. All are valid WPS/PQR. After completion of welding, the whole pressure vessel goes into a furnace for heat treatment.
Question: Is this an NCR? Does the 4th WPS have to be requalified in order to rectify as per ASME IX?
Your responses are very much appreciated.
Scenario: A pressure vessel has four WPS/PQR. Three have PWHT, the 4th WPS/PQR does not have PWHT. All are valid WPS/PQR. After completion of welding, the whole pressure vessel goes into a furnace for heat treatment.
Question: Is this an NCR? Does the 4th WPS have to be requalified in order to rectify as per ASME IX?
Your responses are very much appreciated.