bpcgeo
Geotechnical
- Oct 15, 2015
- 3
Hello, this is my first post but I've read a lot of posts and really like this forum.
I would just like to get some feedback from this forum on additions on piles. Project: Addition to Existing fire station founded on strip footings on very loose to loose sand down to depth of about 42 ft (where dense till was encountered). Preliminary liquefaction analyses based on SPT indicates sand is susceptible to liquefaction and settlements could be in range of 300 to 400 mm.
1) If we recommend piles for addition, I'm worried about the performance of the existing building connected to the addition on piles during earthquakes. If there is an earthquake, won't the two structure behave differently and wont it make it worst that the addition is on piles?
2) If so, would recommending pilling the whole structure the only solution or is it excessive?
3) i have the same question for additions to building founded on soft clays (where major settlement cracks were observed on the existing building), Do you have experience with pilled additions? I have seen structure with soft clay consolidation settlements damages being partially underpinned (piles to rock) and have performed well but I'm always worried about performance during an earthquake. I would like feedback because I have seen some projects (where we were not involved) where additions were built on piles and existing structure most likely on superficial foundations as settlement cracks were observed. I'm wondering if our way thinking is excessive.
thanks
I would just like to get some feedback from this forum on additions on piles. Project: Addition to Existing fire station founded on strip footings on very loose to loose sand down to depth of about 42 ft (where dense till was encountered). Preliminary liquefaction analyses based on SPT indicates sand is susceptible to liquefaction and settlements could be in range of 300 to 400 mm.
1) If we recommend piles for addition, I'm worried about the performance of the existing building connected to the addition on piles during earthquakes. If there is an earthquake, won't the two structure behave differently and wont it make it worst that the addition is on piles?
2) If so, would recommending pilling the whole structure the only solution or is it excessive?
3) i have the same question for additions to building founded on soft clays (where major settlement cracks were observed on the existing building), Do you have experience with pilled additions? I have seen structure with soft clay consolidation settlements damages being partially underpinned (piles to rock) and have performed well but I'm always worried about performance during an earthquake. I would like feedback because I have seen some projects (where we were not involved) where additions were built on piles and existing structure most likely on superficial foundations as settlement cracks were observed. I'm wondering if our way thinking is excessive.
thanks