Texas Piper
Mechanical
- Oct 26, 2020
- 25
Long time lurker, first time poster. I would greatly appreciate the input of the knowledgeable folks here with the following situation as I unfortunately do not have a mentor to turn to.
When doing stress analysis in the past, it was for newly installed systems with no tie-ins to existing lines so I am unsure of how to proceed here.
Project Background: We are relocating an existing pressure reducing valve station for 300# plant steam to allow the plant room for equipment additions. This also involves re-route of several plant steam lines, 300# and 100# as well as condensate lines. This piping ties into a main pipe rack.
Modeling and analyzing the entire existing system is outside our scope so how should I approach modeling the reaction at the existing tiepoints? I was thinking downstream of the tiepoints in the rack I would just include a straight run length of maybe 100’ with the associated supports, assuming it is restrained except for axial movement. The piping upstream of the 300# tiepoint is slightly more complex with a few directional and elevation changes. I was thinking of including the first few changes until it hits a ~100’ straight run out of the building again assuming it is restrained except for axial movement.
Attached is a plan view sketch to illustrate what I’m talking about. Please note that this in a very congested plant and the routing is done so to clear existing conditions.
Thank you for your input.
When doing stress analysis in the past, it was for newly installed systems with no tie-ins to existing lines so I am unsure of how to proceed here.
Project Background: We are relocating an existing pressure reducing valve station for 300# plant steam to allow the plant room for equipment additions. This also involves re-route of several plant steam lines, 300# and 100# as well as condensate lines. This piping ties into a main pipe rack.
Modeling and analyzing the entire existing system is outside our scope so how should I approach modeling the reaction at the existing tiepoints? I was thinking downstream of the tiepoints in the rack I would just include a straight run length of maybe 100’ with the associated supports, assuming it is restrained except for axial movement. The piping upstream of the 300# tiepoint is slightly more complex with a few directional and elevation changes. I was thinking of including the first few changes until it hits a ~100’ straight run out of the building again assuming it is restrained except for axial movement.
Attached is a plan view sketch to illustrate what I’m talking about. Please note that this in a very congested plant and the routing is done so to clear existing conditions.
Thank you for your input.