I am working on project for hydrostatic testing of ball valve according to API 598. In this project, I am clamping the valve using hydraulic cylinder, Once valve has been clamped, pump wil start pumping the water and valve will start filling with water. I am planing to fill this valve vertically from downside fixture plate to remove air from valve from upper fixture plate and arrangement of holes has been made in the clamping fixture plates.
I am planing this whole experiment in such a way that you need to push button only once valve will be clamped properly. When you will push button pump will start pumping the water and once pressure is acheived timer will start and timer is stopped, valve will be drained from bottom side and cylinder will be retracted. this whole cycle will take only effort of putting valve on fixture plate and pressing the button.
But my only concern is While filling the valve i have to be sure that all air has been removed from valve before test pressure is acheived and for that i have provided hole on upper plate so, once operator observes that water is only coming out and all air has been removed then he will shut off the valve that is attached with that plate and pressure will start developing in valve.
In my whole project this is the only thing for which i am not getting any idea to consider it with automatic cycle that i have designed. I need a help for this that how can i make it auytomatic so at the end i need to push the button only and once air is removed it is automatically identified and solenoid valve there will close automatically.It kind of looking like in whole automatic/ Semi-automatic cycle only this thing of removing air during filling of valve is manual i want to automise it.
I need ideas and suggestion for this thing.
Thank you!
I am working on project for hydrostatic testing of ball valve according to API 598. In this project, I am clamping the valve using hydraulic cylinder, Once valve has been clamped, pump wil start pumping the water and valve will start filling with water. I am planing to fill this valve vertically from downside fixture plate to remove air from valve from upper fixture plate and arrangement of holes has been made in the clamping fixture plates.
I am planing this whole experiment in such a way that you need to push button only once valve will be clamped properly. When you will push button pump will start pumping the water and once pressure is acheived timer will start and timer is stopped, valve will be drained from bottom side and cylinder will be retracted. this whole cycle will take only effort of putting valve on fixture plate and pressing the button.
But my only concern is While filling the valve i have to be sure that all air has been removed from valve before test pressure is acheived and for that i have provided hole on upper plate so, once operator observes that water is only coming out and all air has been removed then he will shut off the valve that is attached with that plate and pressure will start developing in valve.
In my whole project this is the only thing for which i am not getting any idea to consider it with automatic cycle that i have designed. I need a help for this that how can i make it auytomatic so at the end i need to push the button only and once air is removed it is automatically identified and solenoid valve there will close automatically.It kind of looking like in whole automatic/ Semi-automatic cycle only this thing of removing air during filling of valve is manual i want to automise it.
I need ideas and suggestion for this thing.