Sofistioelevib
Industrial
- Jun 24, 2015
- 99
Hello to everyone,
i have a transformer ABB ADDA, 35MVA, ONAN TYPE, pri:138KV sec:11KV with only primary and secondary winding oil radiant cooling system.
132KV line is a star connection and secondary is delta connection.
The connection is 132KV line >> trafo >> generator 11KV
Consider generator disconnected so no load on transformer.
Going to energize transformer from 132KV and consider the magnetization current, how many energization i can make in a day?how many in hour?
Someone says no problem to energize many time, some other 2 energization in a day is too much. Who have right? and why?
Thank you
i have a transformer ABB ADDA, 35MVA, ONAN TYPE, pri:138KV sec:11KV with only primary and secondary winding oil radiant cooling system.
132KV line is a star connection and secondary is delta connection.
The connection is 132KV line >> trafo >> generator 11KV
Consider generator disconnected so no load on transformer.
Going to energize transformer from 132KV and consider the magnetization current, how many energization i can make in a day?how many in hour?
Someone says no problem to energize many time, some other 2 energization in a day is too much. Who have right? and why?
Thank you