vincentpa
Structural
- Nov 9, 2005
- 223
Hello,
I am working with a contractor to rehabilitate a nuclear facility built in the 1950’s which was contaminated in a small meltdown in 1960. The majority of the building is concrete and heavy construction. The contamination in the concrete is removed by scabbling or shaving the concrete surface. The surface in question is a concrete beam and one-way slab system with the slab poured integrally with the beams. The slab is 8” thick with ¾” cover top and bottom and the beams are 20” x 36”. What is the minimum cover to still have the top and bottom bars effective in bending? Can we shave or remove the top bars completely in the one-way slab? I’m not sure where the crack will occur if we remove the top bars in the slab entirely. It seems the compression strut will still be in the slab and the slab will just act as a simple support if we remove the top layer of rebar. Is this true?
We are also analyzing a 1’-6” retaining wall that spans horizontally with 2” of cover retaining 32’ of soil. The walls are contaminated. Can we remove the cover to the bar?
I have a complete set of ACI manuals. I just don’t know where this information would be contained. I see bridges with spalled abutments, columns, and beams to the rebar and they seem to function well. What are your thoughts regarding the effectiveness of the rebar with minimal cover or no cover?
Thank you,
I am working with a contractor to rehabilitate a nuclear facility built in the 1950’s which was contaminated in a small meltdown in 1960. The majority of the building is concrete and heavy construction. The contamination in the concrete is removed by scabbling or shaving the concrete surface. The surface in question is a concrete beam and one-way slab system with the slab poured integrally with the beams. The slab is 8” thick with ¾” cover top and bottom and the beams are 20” x 36”. What is the minimum cover to still have the top and bottom bars effective in bending? Can we shave or remove the top bars completely in the one-way slab? I’m not sure where the crack will occur if we remove the top bars in the slab entirely. It seems the compression strut will still be in the slab and the slab will just act as a simple support if we remove the top layer of rebar. Is this true?
We are also analyzing a 1’-6” retaining wall that spans horizontally with 2” of cover retaining 32’ of soil. The walls are contaminated. Can we remove the cover to the bar?
I have a complete set of ACI manuals. I just don’t know where this information would be contained. I see bridges with spalled abutments, columns, and beams to the rebar and they seem to function well. What are your thoughts regarding the effectiveness of the rebar with minimal cover or no cover?
Thank you,