failuremode
Structural
- May 6, 2021
- 6
I am working on a transformer replacement project. The new transformer (~330kip) will be located at the same location as the existing transformer so they want to reuse the existing foundation elements as much as possible. The existing foundation is a 3ft 'T' shaped pile cap on (9) 18" dia precast piles - circa 1960s. The new slab poured over the top of the existing foundation will be 20ftx14ftx~2ft thick with an additional (4) 3ft diameter piers in the corners to avoid overstressing the extreme existing piles.
Any thoughts on how to analyze this configuration?
In the image - Blue is existing. Magenta is new.
Any thoughts on how to analyze this configuration?
In the image - Blue is existing. Magenta is new.