SperlingPE
Structural
- Dec 27, 2002
- 591
I received a field observation report concerning anchor rods being placed in the following manner:
1. footing excavation is filled with concrete
2. concrete is consolidated mechanically
3. top of footing is smoothed (troweled)
4. anchor rods are pushed into concrete and set to elevation
5. sometimes the stinger is re-inserted into the concrete after the anchor rods are placed.
I have never seen this. My typical experience is that the anchor rods are set to elevation and the concrete is poured around anchor rods and then consolidated.
Is there a problem with the first procedure outlined above?
My thought is that the concrete that is counted on if the anchor rod is subjected to tension is not in place.
Thoughts?
Is there a field test (ASTM) that can be performed to verify anchor rods?
1. footing excavation is filled with concrete
2. concrete is consolidated mechanically
3. top of footing is smoothed (troweled)
4. anchor rods are pushed into concrete and set to elevation
5. sometimes the stinger is re-inserted into the concrete after the anchor rods are placed.
I have never seen this. My typical experience is that the anchor rods are set to elevation and the concrete is poured around anchor rods and then consolidated.
Is there a problem with the first procedure outlined above?
My thought is that the concrete that is counted on if the anchor rod is subjected to tension is not in place.
Thoughts?
Is there a field test (ASTM) that can be performed to verify anchor rods?