Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Another Winter Construction Question

Status
Not open for further replies.

DarthSoilsGuy

Geotechnical
Oct 31, 2006
237
Hello, first-time poster but I've been reading posts for 2 years now.

i've got a job where the high has been below freezing for two weeks with lows getting down to near zero.

The contractor/owner/client has poured some interior footings (3x3x12")on 8" of crushed washed stone on ground that may have frozen underneath it. (He backfilled 20" with crushed washed gravel for the reast of the SOG area to Top of ftg/bottom of slab)

He wants to pour his SOG soon and asked me if I thought he would be able to if he enclosed the area and heated it for a week. I told him it might work but the only way to know would be to dig a hole. Basically, I don't know enough about this since I'm from the South and up in Vermont now.
Does anyone know a good link, thread, or want to comment?


 
Replies continue below

Recommended for you

A steel rod driven into the sub-grade can make a hole to insert a thermometer. Five minutes to stabilize temps and then read the thermometer, easier than digging and three locations can be checked for a good average. The week might be excessive if lots of heaters and good enclosure used.
 
hamhodgman....if you would have stayed in NC, and not moved to Vermont, you would not have this problem/question!! Miss u man!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor