How do other folks approximate dimensions on their drawings? For example, when I have a foundation plan based on a rather weak set of building plans (residential projects do not always have complete architectural drawings) I will usually put +/- after my dimensions and follow that with a note to contractor to verify dimensions in field. Same thing applies to remodel projects where dimensions are based on someone else's tape measure.
A colleague of mine told me +/- is not technically correct since 10' +/- could mean either 9' or 11'. All I am trying to say is that dimension should not be relied on as for sure number without checking first and slight modification is acceptable. Is there a better way?
A colleague of mine told me +/- is not technically correct since 10' +/- could mean either 9' or 11'. All I am trying to say is that dimension should not be relied on as for sure number without checking first and slight modification is acceptable. Is there a better way?