timsch
Mechanical
- Oct 27, 2009
- 181
Our company manufactures multipoint thermocouple assemblies that are designed to the current ASME BPVC SEC.VIII, DIV.1. Frequently we get orders for replacement assemblies, with no changes, and I get requests for updated calculations based on the latest release of the BPVC. I thought I read somewhere in VIII, DIV.1, that a design could be accepted based on proven service of the same design with no additional calculations required. I looked through the 2015 version, and could not find any such justification.
Perhaps I am just thinking of wording from other section of the code, such as piping. Are calculations to the latest version required for these instances?