Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Area Required for Waste Water Treatment 1

Status
Not open for further replies.

arj00

Civil/Environmental
Jan 7, 2003
13
0
0
RU
The Municipality has to allocate a new site for a tertiary treatment activated sludge to handle 1 million m3/day (264 million gallons/day).
What is the minimum area needed to provide tertiary treatment for such a plant including sludge treatment.
 
Replies continue below

Recommended for you

Difficult to answer your question directly. There is no "standard" size. You may have to survey similar plants in your area which should give you a pretty good idead of about how much space may be needed for a 1 MGD plant. You may also find some information from the US EPA Regional office including a rough idea of construction costs.

good luck
 
If this sizing figure is Average Dry Weather Flow, you are talking about a very large plant. 1000ML/day ADWF is equivalent to the load from a city of around 4 million people. Is this correct?

I strongly suggest you engage a consultant to prepare you some concept layouts for a plant this size, as there could be big differences in footprint, depending on the process selected.

It seems you will have some very important land acquisition issues depending on the answer!

Mail me back if you need more help.

Aussie Mike.
 
Status
Not open for further replies.
Back
Top