Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

As-Built Piling Plan

Status
Not open for further replies.

drago8

Civil/Environmental
Jun 26, 2015
41
Dear All,

I have an enquiry. For an as-built plan, does it have to include all the eccentricities in the drawings? or just those eccentricities that exceed pile tolerances?

Actually, what are the standard requirements or what must to be shown on the as-built piling plan?

Thank you.

#LoveWins
 
Replies continue below

Recommended for you

Regarding your inquiry: we don't know how your piles are being used (under a building, supporting equipment foundations, etc.). However, if these piles are under a building foundation, then around here, our record drawings only specifically note those piles which are out of tolerance, moved, replaced, or supplemented. I hope this makes your job simpler.
Dave

Thaidavid
 
Dear thaidavid40,

Thanks for your response. So it does not necessarily need to indicate the eccentricities within the pile tolerance? Then, for those piles which are moved but within the tolerance, you will just provide Pile Eccentricity Report/Summary to the consultants?

Thanks

#LoveWins
 
By moved, I mean a pile which has been shifted intentionally to some out-of-tolerance location. This usually happens when an underground obstruction prevents driving a pile to its intended depth. It would necessarily then be noted as such in the record drawings.
Dave

Thaidavid
 
What do the Contract documents say? Typically, they will require Contractor to note deviations from the Contract only. However, on our marine pile projects, we require actual pile locations be determined by the Contractor based on a legal survey.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor