OzEng80
Structural
- Jan 8, 2006
- 147
AS3600 states the 20db is required to develop a bar in compression. It is also states that to achieve a lapped splice in compression (0.125fsy-22)db = 40db (for fsy=500) (32db if you have ligs) is required.
What is the basis of this difference? The commentary gives some history but not reasoning.
Also what are the scenarios where a bar is required to be developed in compression?
Do column starters bars need to be developed in compression and the vertical bars lapped accordingly (32db)? Or is this only required if fixity is assumed in the connections?
Thanks!
What is the basis of this difference? The commentary gives some history but not reasoning.
Also what are the scenarios where a bar is required to be developed in compression?
Do column starters bars need to be developed in compression and the vertical bars lapped accordingly (32db)? Or is this only required if fixity is assumed in the connections?
Thanks!