ShawThing
Structural
- Aug 17, 2017
- 46
Hi
Currently involved in a project where a commercial building is being converted into residential units.
The roof structure consists of steel roof trusses at 6m centres as the primary roof members which support purlins. The bottom chord of the truss has fly bracing each side at regular centres.
As part of this project the fly bracing is proposed to be removed and a fire rated stud wall constructed immediately adjacent each side of the trusses forming the party wall between the units. The fire rated walls each side of the truss will be back to back 76mm steel studs at 450 centres. This design has been supplied by the fire engineer.
Trying to justify the removal of the existing fly bracing utilising the steel stud walls by providing a connection between the stud wall and the truss bottom chord and I'm not quite following the explanation in clause 6.6.3 of AS4100. Have calculated 2.5% of the compression force in the bottom chord of the truss. Say the fly braces are at 3600mm centres. Am I allowed to divide that load by 7 (referenced in clause 6.6.3) to calculate the load on each double stud?
Hope I have explained this sufficiently.
Cheers.
Currently involved in a project where a commercial building is being converted into residential units.
The roof structure consists of steel roof trusses at 6m centres as the primary roof members which support purlins. The bottom chord of the truss has fly bracing each side at regular centres.
As part of this project the fly bracing is proposed to be removed and a fire rated stud wall constructed immediately adjacent each side of the trusses forming the party wall between the units. The fire rated walls each side of the truss will be back to back 76mm steel studs at 450 centres. This design has been supplied by the fire engineer.
Trying to justify the removal of the existing fly bracing utilising the steel stud walls by providing a connection between the stud wall and the truss bottom chord and I'm not quite following the explanation in clause 6.6.3 of AS4100. Have calculated 2.5% of the compression force in the bottom chord of the truss. Say the fly braces are at 3600mm centres. Am I allowed to divide that load by 7 (referenced in clause 6.6.3) to calculate the load on each double stud?
Hope I have explained this sufficiently.
Cheers.