bmoorthy
Mechanical
- May 29, 2003
- 457
While i have asked for a question in Boiler and PV Forum,on the related subject, this question is slightly different from that one, hence in this forum
Please refer to the Clause 7.4 from A 420 WPL6
7.4 When the fittings are to be post-weld heat treated after being welded by the purchaser and when so specified in the order, the test specimens shall be subjected to the same post-weld heat treatment. The purchaser shall use the postweld heat treatment shown in Table 2, unless otherwise
specified in the order.
If One orders a fitting fo 20" diameter 25 mm thick (Beveled butt weld ends) and this is going to be used for welding in the piping (The Specification that went to the fitting manufactuer clearly specifies that the fitting are meant for the welding on ANSI/ASME B 31.3 piping),
1) is it necessary that the fitting manufacturer test the specimen after PWHT? (because it is a well known fact that any welding beyond 19mm requires PWHT as per B 31.3-For butt joints)
2) Is it the responsibility of the purchaser to specify that the fitting will be subject to PWHT?
3) if the purchaser did not specify and supplier supplied the fittings as per standard (Not testing after simulated heat treatment, but only after the heat treatment that the fitting under went at the fitting manufacturing shop), is it OK to use in B 31.3 piping system and heat treat them (With out performing any additonal destructive tests)
Please refer to the Clause 7.4 from A 420 WPL6
7.4 When the fittings are to be post-weld heat treated after being welded by the purchaser and when so specified in the order, the test specimens shall be subjected to the same post-weld heat treatment. The purchaser shall use the postweld heat treatment shown in Table 2, unless otherwise
specified in the order.
If One orders a fitting fo 20" diameter 25 mm thick (Beveled butt weld ends) and this is going to be used for welding in the piping (The Specification that went to the fitting manufactuer clearly specifies that the fitting are meant for the welding on ANSI/ASME B 31.3 piping),
1) is it necessary that the fitting manufacturer test the specimen after PWHT? (because it is a well known fact that any welding beyond 19mm requires PWHT as per B 31.3-For butt joints)
2) Is it the responsibility of the purchaser to specify that the fitting will be subject to PWHT?
3) if the purchaser did not specify and supplier supplied the fittings as per standard (Not testing after simulated heat treatment, but only after the heat treatment that the fitting under went at the fitting manufacturing shop), is it OK to use in B 31.3 piping system and heat treat them (With out performing any additonal destructive tests)