Bluecat46
Mechanical
- Oct 7, 2011
- 35
How does anyone get round the section 341.4.1 (b) (1) requirement for 5% radiography/ultrasonic on butt and miter welds when doing maintenance/breakdown work when the need is to replace the pipe spool?
Is there another code that I should be looking at for the maintenance on pipe work?
Is there another code that I should be looking at for the maintenance on pipe work?