Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations Danlap on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME BTH-1 Major Axis Bending

KB4444

Civil/Environmental
Nov 29, 2021
23
I am designing a 12.25ft lifting beam that is picked up by lifting lugs on the top flange of the beam. The lifting lugs are welded at the ends, being 12ft (144") apart, which I believe means the unbraced length would be 144"? The load is picked up by lifting lugs on the bottom of the beam spaced uniformly apart.

I am trying to size the beam in bending. Using ASME BTH-1: 3-2.3.1 Major Axis Bending of Compact Sections, I am running into a problem with the unbraced length.

I am finding that I do not have a reasonable beam size that is less then Lp (3-7) or Lr (3-10).

Using a W10x33:

Lp = 1.76 x 1.937" x sqrt(29000ksi / 50 ksi)
= 82"
Lr = sqrt(3.19 x 2.136^2 in^2 x 29000ksi x 1 / 50ksi)
[When the bending moment at any point within an unbraced length is larger than that at both end of this length, Cb shall be taken as unity. Therefore, Cb = 1.0]
= 92"

Lu = 144"?

If I am correct with Lu being the space between supports what is my next step? I wouldn't have Lu < Lr, so I believe I am stuck going to an even larger beam size? The bending stress in this situation wouldn't govern.

Screenshot 2025-02-14 120055.png
 
Replies continue below

Recommended for you

I believe means the unbraced length would be 144"? The load is picked up by lifting lugs on the bottom of the beam spaced uniformly apart.
For your case , Effective length should be LE = 1.2LLT + 2D= 144+2*10= 164 in. ( BS 5950)
Notice that , top and bottom flanges free to rotate on plan.
 
Is the requirement for needing Lr to be more then Lu (or Le) correct?

Using an extremely heavy W12x106 beam:

Lr = sqrt[3.19 x (3.35^2)in^2 x 29000ksi x 1 / 50ksi]
= 144"

So this would be saying that a W12x106 fails if that is required, which already is a beam size that isn't feasible. For a beam supported on only a 12ft span the bending capacity of this option is grossly overdesigned.
 
Use an HSS. HSS are typical for below the hook lifting devices since they cannot buckle laterally (LTB is a prickly thing when there is 0 lateral support, hence the onerous requirements of BTH).
 
If the plates don't line up from loading to support do you need to worry about wall failure using HSS? Simple solution, appreciate the response, just thinking ahead to my next concern?
 
The obvious question for me is why not move the lifting lugs 2'-0" inward at each end. Not only do you decrease the unsupported length from 12' to 8', but the maximum moment is reduced by a factor of about 3. With a uniform load over the full length of beam, the negative moment at each lug is w*2^2/2 = 2w. The positive moment is w*8^2/8 - 2w = 6w. With a 12' span, the positive moment is w*12^2/8 = 18w, three times as much. A W10x33 should work with capacity to spare.
 
Last edited:
If the plates don't line up from loading to support do you need to worry about wall failure using HSS? Simple solution, appreciate the response, just thinking ahead to my next concern?
Yes, you need to check the walls. I typically slot the plates through the walls of the hss and weld both sides, to avoid a heavier HSS.
 
BAretired:
I didn't show above the lifting beam but there are (2) existing monorails that are spaced 12' O.C. so this allows a vertical pickup.

canwesteng:
I will see what I can find for the through plate calculations, thanks for the idea on this.

dvd:
I have not seen this publication, I will review it as well. Thanks.
 
Does't the load cause a restoring moment? Wouldn't that help mitigate LTB?
Seems like it is already near its lowest energy state.
 
Does't the load cause a restoring moment? Wouldn't that help mitigate LTB?
Seems like it is already near its lowest energy state.
This is a salient point. The bottom-flange loads act to rotate the beam back to plumb, at least countering the “torsional” piece of the LTB mechanism.
 
BAretired:
I didn't show above the lifting beam but there are (2) existing monorails that are spaced 12' O.C. so this allows a vertical pickup.
A vertical pickup is not necessary if the monorails can resist the horizontal component of the lifting force. This would require a minimum vertical separation between the monorails and the lifting beam.
 
It's not clear how two monorails twelve feet apart can be used if the load to be picked up is not centered under their midpoint. The load will likely be anywhere on the floor, so it is unrealistic to assume a vertical pickup. An overhead crane capable of spanning the entire floor area is a much better pickup device.
 
The obvious question for me is why not move the lifting lugs 2'-0" inward at each end. Not only do you decrease the unsupported length from 12' to 8', but the maximum moment is reduced by a factor of about 3. With a uniform load over the full length of beam, the negative moment at each lug is w*2^2/2 = 2w. The positive moment is w*8^2/8 - 2w = 6w. With a 12' span, the positive moment is w*12^2/8 = 18w, three times as much. A W10x33 should work with capacity to spare.

Using this revised lifting arrangement I am still getting an issue with the unbraced length posed for the initial problem, Lu > Lr:

Lu = 8'x12"
= 96"

Lr = sqrt[3.19 x (2.14^2)in^2 x 29000ksi x 1 / 50ksi]
= "91.5

Cb = 1 (unity)
rt = 2.14 in^2 (compression flange + 1/3 compression web area)

Due to this I believe the design would need to be increased from a W10x33, even though capacity already is sufficient?
 
Using this revised lifting arrangement I am still getting an issue with the unbraced length posed for the initial problem, Lu > Lr:

Lu = 8'x12"
= 96"

Lr = sqrt[3.19 x (2.14^2)in^2 x 29000ksi x 1 / 50ksi]
= "91.5

Cb = 1 (unity)
rt = 2.14 in^2 (compression flange + 1/3 compression web area)

Due to this I believe the design would need to be increased from a W10x33, even though capacity already is sufficient?
Your calculation does not agree with the CISC handbook for laterally unsupported members. You are from Canada, right?

So Mr for a W10x33 is 178 kN-m and Lu = 3160mm, which is 124" assuming G40.21 steel with a yield of 350 kN-m.
At 2500mm, A W10x33 is good for the full Mr, so your calculation appears conservative by comparison.

You seem to be deriving your expression from the ASCE standard with which I am not familiar, but it appears to be ultra conservative.

In any case, it appears to me that you cannot rely on a vertical pickup, because the load could be remote from the monorails.
 
Last edited:

Part and Inventory Search

Sponsor