Jerry k
Mechanical
- Oct 16, 2021
- 4
Hi All,
I may need your expertise on this matters.
Currently, I'm on the storage tank construction project. Very small tank, only 4 meters diameter. The scope is to fabricate a new tank, remove the old tank and replace with new tank. In the previous issue of the drawing, the existing tank was design with BS 2654 code and the construction code is EN 14015. The client want us to follow BS EN standard for the WPS & Welder qualifications.
The situation is that, the company I worked at now only have ASME IX WPS. And their ASME IX WPS is very general compared to BS EN Standard (e.g. Type of weld; fillet weld for fillet weld only, butt weld for butt weld only). But in the contract requirement stated that the welders qualifications shall accordance to the ASME IX. But the Client Inspection team keep saying refer to the code, must comply to the code.
I've tried to argue. As per ISO 15614-1:2017 have mentioned in the introduction there is two level of welding procedure given. They are designated by level 1 and level 2. Level 1 is based on requirements of ASME Section IX and level 2 is based on the previous issues of ISO 15614. But in the end, the argument still back to the essential variables requirements and I'm out of words.
The project have started, and all the materials cutting are in progress. But we cannot do the assembly due to this matters. Is there anyway I can bring in ASME IX WPS for this project ?.
Thank you.
Jerry
I may need your expertise on this matters.
Currently, I'm on the storage tank construction project. Very small tank, only 4 meters diameter. The scope is to fabricate a new tank, remove the old tank and replace with new tank. In the previous issue of the drawing, the existing tank was design with BS 2654 code and the construction code is EN 14015. The client want us to follow BS EN standard for the WPS & Welder qualifications.
The situation is that, the company I worked at now only have ASME IX WPS. And their ASME IX WPS is very general compared to BS EN Standard (e.g. Type of weld; fillet weld for fillet weld only, butt weld for butt weld only). But in the contract requirement stated that the welders qualifications shall accordance to the ASME IX. But the Client Inspection team keep saying refer to the code, must comply to the code.
I've tried to argue. As per ISO 15614-1:2017 have mentioned in the introduction there is two level of welding procedure given. They are designated by level 1 and level 2. Level 1 is based on requirements of ASME Section IX and level 2 is based on the previous issues of ISO 15614. But in the end, the argument still back to the essential variables requirements and I'm out of words.
The project have started, and all the materials cutting are in progress. But we cannot do the assembly due to this matters. Is there anyway I can bring in ASME IX WPS for this project ?.
Thank you.
Jerry