Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME VIII Div I certification

Status
Not open for further replies.

Spoonful

Mechanical
Oct 18, 2008
175
Hi All,

In order to have a vessel certified to ASME Code, it has to be manufactured by a U stamp holder, but dose the designer of the vessel have to ASME certified?
Any direction of relevant code section to read?

Thanks
 
Replies continue below

Recommended for you

Spoonful, you don't specify but the reference to U Stamp implies Sec VIII, Div 1. Answer is no. I am not aware of any Sec VIII, Div 1 provision that addresses designer qualifications one way or the other.

Regards,

Mike
 
I agree with SnTMan, the manufacturer ultimately takes responsibility, so the ability or qualifications of the designer are irrelevant.
 
"...the ability or qualifications of the designer are irrelevant."

Just one of the things that make this line of work SO rewarding, thanks TGS4:)
 
I know SnTMan. You're preaching to the choir. Sigh....
 
The manufacture is under the directive of the designer, at least in regarding with the vessel design, should the design be at lest somehow liable?
 
Spoonful, even when meeting all relevant Code rules and employing the best engineering judgement the designer is always potentially liable for the design. As in any field.

Regards,

Mike
 
Thanks Mike, my question was just refer to per TGS4 said, the ultimate responsibility goes to the manufacture.
 
Spoonful - from the perspective of the Code, there are no responsibilities for the designer (yet). All responsibility rests on the manufacturer. If the manufacturer contracts out design services, then there may be contractual obligations.
 
Hi TGS4, what if it is the other way around, the designer got the job and designed the vessel and then subcontract the fabrication to the manufacture?
 
This is so relavent in today's times. It is hard to find any experienced people in the 10yr to 30 year range.

all the new engineers want to plug it in the computer and what is spits out is correct.

They have no idea what to change and when to change it.
 
Spoonful, ultimate responsibilty still rests with the manufacturer. However: As the party contracting out the fabrication it is incumbent upon the design entity to insure the fabricator is meeting his responsibilities.

Regards,

Mike
 
From ASME's perspective, I believe that what SnTMan said is correct - the responsibility is with the manufacturer, the holder of the U-Stamp (or its current incarnation). Everything else is a commercial/contractual concern. Is it important, yes; is it a requirement of the Code, no.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor