Our scope of work is to do asphalting for a 2.2 KM double cell 8-meter width tunnel, the clear height of the tunnel is around 7 meters and asphalt trucks will not be capable of doing the tipping operation. therefore we need a special material handling system to deliver the hot asphalt into the tunnel ( from the truck to the paver hopper).
Any past experience with using cascaded screw conveyors to transfer the Hot Asphalt Batch from the gate of the tunnel (continually) to the paver point??
One of the cases similar to our case is the Catesby Racing Tunnel which is converted from a railway tunnel to super car Formula 1 Testing tunnel as a wind tunnel. very limited working height
Tarek Barham
+971563188219
tarek@zadconsult.com
Any past experience with using cascaded screw conveyors to transfer the Hot Asphalt Batch from the gate of the tunnel (continually) to the paver point??
One of the cases similar to our case is the Catesby Racing Tunnel which is converted from a railway tunnel to super car Formula 1 Testing tunnel as a wind tunnel. very limited working height