Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Associativity checkbox comes and goes in Sketcher

Status
Not open for further replies.

acciardi

Computer
Jun 6, 2006
143
Hello all:

I'm using NX 5.0.4.1, but I've noticed this behavior for quite a while.

While in sketcher, I often select the 'project' icon to pick existing geometry to use in the sketch.

Sometimes it is desired to make this geometry associative, but the 'associativity' checkbox is ghosted. Other times, the checkbox is available. It doesn't matter what the selection filter is set to. I haven't noticed a pattern, so I was wondering if there is some rule that I'm not aware of.

Thanks in advance,

Ed
 
Replies continue below

Recommended for you

Are you saying that you toggle it off but it comes back on during a given session or from one session to the next or even from one sketch to the next. The only thing that I can see is that for me it was on by default, then once I turned it off and I went through with a curve projection it stayed set that way, but if I backed out of the projection operation it went back to on.

Cheers

Hudson
 
Hudson:

It toggles on and off by itself during a session, and even during a sketch.

I may have it available the first time I try to project some edges, but on subsequent tries it is ghosted.

Ed
 
If you're Sketching in the context of a Drawing, the Associative option in Project Curve is grayed-out. When Sketching in a model view, whether in Drafting or Modeling, just as long as you're NOT in the Drawing itself, the Associative option should be available (not grayed-out).

John R. Baker, P.E.
Product 'Evangelist'
NX Design
Siemens PLM Software Inc.
Cypress, CA
 
John:

I am seeing the greyed-out behavior in the modeling application.

In the attached screesnot, I am in the modeling application editing a sketch. I would like to project an existing model edge into the sketch plane and make it associative, but the checkbox is ghosted.

Ed
 
 http://files.engineering.com/getfile.aspx?folder=8d00f30f-d9f6-41c8-9954-82ba4043535d&file=screenshot.jpg
OK, I think I know what's happening although I'm not sure what the issue was that prevented us from making the software work the way you would like it to, and in all honesty looks like it should.

Except for the Drafting case, which I've already confirmed but which is NOT relevant here, it appears that this has to do with what we are not allowing during the editing of an embedded sketch. From your image it appears that you are editing an embedded sketch using edit with roll-back and in this case the system, for some reason, is not going to permit you to create a new associative projection (you had no problems doing something like this during the initial creation of the sketch, embedded or otherwise, however, now you're being restricted from doing so. And before you ask, I can't see what the problem could be that we were worried about and therefore are probably trying to protect you from.

As for a workaround, if you were to first un-embed the sketch (make it external) you can edit it without being restricted in what you can do in terms of adding a new associative projection. Then once your edit is compete and the model has been updated, just make the sketch internal again.

Now for the GOOD news, whatever the issue was, we appear to have overcome it (or at least figured out that there wasn't a problem in the first place) and so in NX 6 the ability to create an Associative Projection works the same whether you're creating or editing a sketch irrespective of whether it's embedded or not. There appears to no longer be any restrictions in this area while working in Modeling (it's still grayed-out in Drafting, but I'm not too surprised about that).

And as a sanity check, the model that I created in NX 5 to test your problem and where I found what you did, I filed that part and opened it in NX 6 and I was now able to edit those embedded sketches and create Associative Projections where in NX 5 I would have seen just the grayed-out option, so it would appear that we have fixed the 'problem', whatever it was ;-)

Now before you ask, I wouldn't hold my breath expecting us to make any changes in NX 5 since you do have a procedure (my workaround above) that will permit you to get your job done.

John R. Baker, P.E.
Product 'Evangelist'
NX Design
Siemens PLM Software Inc.
Cypress, CA
 
Ah, thanks John. I tend to use a separate sketch for each feature, so it makes sense to me to embed them within the feature.

What I've been doing all this time is to project the existing edge non-associatively and then adding constraints, which accomplishes what I want but is a little slower.

Thanks for the prompt reply.

Ed
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor