plantprowler
Chemical
- Aug 10, 2013
- 136
While witnessing a Pressure Vessel Hydrotest in progress I got thinking: Just out of curiosity how close could we be at that point to structural failure of the Pressure Vessel, given the typical factors of safety in the design codes?
i.e. The test was being performed at 1.3 times the MAWP & the vessel was a SS316 Hydrogenator approx. 8 kL capacity.
So typically at what further pressure would the vessel fail? I suppose there will be some statistical variation but just wondering how much margin is left at the 1.3xMAWP point of test.
Or is there no good general answer to this question & it would depend hugely on the specific design?
i.e. The test was being performed at 1.3 times the MAWP & the vessel was a SS316 Hydrogenator approx. 8 kL capacity.
So typically at what further pressure would the vessel fail? I suppose there will be some statistical variation but just wondering how much margin is left at the 1.3xMAWP point of test.
Or is there no good general answer to this question & it would depend hugely on the specific design?