Dear All.
I have today a hot discaussion with designer and end-user.
We have programmed and commissionied some ATS ( two infeedes and coupler) for the 6.6kV.
Load is lot of async. motors. Designer didn't include in the system deadbus check. I request it, end-user was against
deadbus check too. OK, I will provide what them want, but from my point of view isn't right and always we do in our systems: double criterions, infeed open and deadbus check.
What is your opinion?
Thanks in advance
Regards.
Slava
I have today a hot discaussion with designer and end-user.
We have programmed and commissionied some ATS ( two infeedes and coupler) for the 6.6kV.
Load is lot of async. motors. Designer didn't include in the system deadbus check. I request it, end-user was against
deadbus check too. OK, I will provide what them want, but from my point of view isn't right and always we do in our systems: double criterions, infeed open and deadbus check.
What is your opinion?
Thanks in advance
Regards.
Slava