Someone knows the way to make the microsoft project assign the resources automatically?
For example i have a task that can be executed from 2 different resources. How can i do to make the program assign automatically one of the two, for example the one that terminates her previous tasks before than the other?
Thanks for your answers already from now.

 
Replies continue below

Recommended for you

I don't think there is an automatic way to do that, since the assignment of resources in Project is a manual affair.

The Assignment_delay field is supposed to tell you when a resource can be assigned, given the current workload.