cbradley75
Electrical
- Jan 14, 2010
- 8
I'm hoping someone here is familiar with this approach. The utility I came from before relocating to Georgia never used such a practice. The basic issue is this: Say you have a transmission substation (100kV and above) that is constructed in the single bus configuration (i'm assuming because it's cheapest). Next you have a bus diff relay operate and clear the bus. A few seconds later, this scheme is such that a 'test-breaker' comes closed to test the bus and if the fault is gone, all the other breakers on the bus reclose.
Does anyone know the background of that scheme or seen it elsewhere? Is it unique to georgia? I'm curious because I'm trying to get a good rule of thumb on how I choose which line breaker should be the 'test-breaker' for the bus.
Thanks
"Don’t argue with idiots. They drag you down to their level and beat you with experience."
--Greg King, Comedian
Does anyone know the background of that scheme or seen it elsewhere? Is it unique to georgia? I'm curious because I'm trying to get a good rule of thumb on how I choose which line breaker should be the 'test-breaker' for the bus.
Thanks
"Don’t argue with idiots. They drag you down to their level and beat you with experience."
--Greg King, Comedian