onealexis
Structural
- Aug 8, 2006
- 19
Hi All, looking for some assistance in interpreting AWWA D100-11 as far as how many radiographic tests are to be performed and in what locations.
We have two water tanks, each with a diameter of 37'. The tank is comprised of 5 bands with full-pen welds at the seams between the bands and also at the individual segments making up each band. The tanks are being constructed one after the other with the same welders. I calculated that we have a total of about 1300LF of weld.
We are using Section 11.5 to determine the number and location of the tests, but among two groups at our office have two different interpretations.
One interpretation of the code is that you take the total number of LF and divide it by 100' and that what you come up with is the total number of tests to be performed, but that those tests need not be taken any higher than 8' (the height of one level of scaffold.
The other interpretation is that the tests should be performed as the work progresses and one test is to be taken in each 100LF of weld (as the work progresses or progressed).
Does anyone have enough experience with this code to say or know? Can you help us understand in a way that will convince the opposite party the interpretation provided is accurate?
Thanks much.
We have two water tanks, each with a diameter of 37'. The tank is comprised of 5 bands with full-pen welds at the seams between the bands and also at the individual segments making up each band. The tanks are being constructed one after the other with the same welders. I calculated that we have a total of about 1300LF of weld.
We are using Section 11.5 to determine the number and location of the tests, but among two groups at our office have two different interpretations.
One interpretation of the code is that you take the total number of LF and divide it by 100' and that what you come up with is the total number of tests to be performed, but that those tests need not be taken any higher than 8' (the height of one level of scaffold.
The other interpretation is that the tests should be performed as the work progresses and one test is to be taken in each 100LF of weld (as the work progresses or progressed).
Does anyone have enough experience with this code to say or know? Can you help us understand in a way that will convince the opposite party the interpretation provided is accurate?
Thanks much.