BlueSandman
Mechanical
- Oct 15, 2010
- 4
Does table 314.2.1 apply to my situation below?
I changed companies (same work, new face), and this table just came to light.
The company builds low pressure, low volume natural gas equipment (<2" NPT, under 5 PSIG) for use in industrial factories. Per table above it seems we need to use schedule 80 piping. In doing this for 20 years I have never seen anyone use schedule 80 piping (me, or the competition).
Am I improperly interpreting the application of this table? The building piping feeding my equipment is always schedule 40. Should I be using B31.9 instead?
I changed companies (same work, new face), and this table just came to light.
The company builds low pressure, low volume natural gas equipment (<2" NPT, under 5 PSIG) for use in industrial factories. Per table above it seems we need to use schedule 80 piping. In doing this for 20 years I have never seen anyone use schedule 80 piping (me, or the competition).
Am I improperly interpreting the application of this table? The building piping feeding my equipment is always schedule 40. Should I be using B31.9 instead?