TiCl4
Chemical
- May 1, 2019
- 616
There is a point of B31.3 that I am not clear on. We are installing some new piping that will tie into current piping. The piping is fairly simple - just pipe, fittings, and valves. We will be doing a 1.5X hydro on the system, and had a question about when that test could be completed.
Must the completely assembled piping system be fulling installed before hydrotesting? I.E. must the entire system - all valves and piping segments - be in-place, supported, etc before hydrotesting? In this case, there would be pancake blinds to separate it from the already-installed header for the pressure test.
Or, could the piping be tested separately and before installation in the field? If so, could each piping spool be tested individually (each end blinded off and pressure tested)? Is this allowed under 345.2.3(a)?
If the latter method is allowed and done, is there any requirement for a leak test for the fully assembled piping system?
Must the completely assembled piping system be fulling installed before hydrotesting? I.E. must the entire system - all valves and piping segments - be in-place, supported, etc before hydrotesting? In this case, there would be pancake blinds to separate it from the already-installed header for the pressure test.
Or, could the piping be tested separately and before installation in the field? If so, could each piping spool be tested individually (each end blinded off and pressure tested)? Is this allowed under 345.2.3(a)?
If the latter method is allowed and done, is there any requirement for a leak test for the fully assembled piping system?