Hi
Does anyone have recommed way of checking piping to B31E with Autopipe?
I see my options are
1. Copy the model, change to operating pressure and increase the allowable stress to 2.4/1.2 =2*S. Then look at the occasional code stress check.
(note to use corroded thickness for t and Z)
2. In the piping model change to operating P and modify each load cases in the occasional code combination for EQ by 1.2/2.4 =0.5
thanks
Does anyone have recommed way of checking piping to B31E with Autopipe?
I see my options are
1. Copy the model, change to operating pressure and increase the allowable stress to 2.4/1.2 =2*S. Then look at the occasional code stress check.
(note to use corroded thickness for t and Z)
2. In the piping model change to operating P and modify each load cases in the occasional code combination for EQ by 1.2/2.4 =0.5
thanks