Dear fellow Engineers
Our designer has proposed a backfill on top on concrete and confined by concrete on 3 sides by concrete. The designer has proposed to use a Cohesion less/ free draining material for this purpose and relative density of 80%. The backfill will be carrying the weight of the whole RCC intake structure along with intake gates and trash rack.
Now my query lies :
1. in the settlement of the backfill and how can I determine its expected settlement before the job.Or more specifically should I be worried about the settlement in this case.
2. Also since the backfill is exposed on the abutment on one side(as said earlier the backfill is confined on 3 sides by concrete)should I be worried about the ingress of water into the backfill and fear the possibility of bulking of the cohesion less backfill.However there is drainage pipe provided at the bottom.
3. Also am I wrong to assume that the RD of 80 % which is minimum which could be achieved without compaction and by the virtue of its own weight. I am asking this because the designers has asked to compact in layers of not more 300 mm. Since a CL material needs a vibration for compaction and I am reluctant to use a roller in a concrete structure. Will the manual hand compactors work in this case?
PS: I have uploaded a a rough drawing of the structure for your reference.
KARMA
Our designer has proposed a backfill on top on concrete and confined by concrete on 3 sides by concrete. The designer has proposed to use a Cohesion less/ free draining material for this purpose and relative density of 80%. The backfill will be carrying the weight of the whole RCC intake structure along with intake gates and trash rack.
Now my query lies :
1. in the settlement of the backfill and how can I determine its expected settlement before the job.Or more specifically should I be worried about the settlement in this case.
2. Also since the backfill is exposed on the abutment on one side(as said earlier the backfill is confined on 3 sides by concrete)should I be worried about the ingress of water into the backfill and fear the possibility of bulking of the cohesion less backfill.However there is drainage pipe provided at the bottom.
3. Also am I wrong to assume that the RD of 80 % which is minimum which could be achieved without compaction and by the virtue of its own weight. I am asking this because the designers has asked to compact in layers of not more 300 mm. Since a CL material needs a vibration for compaction and I am reluctant to use a roller in a concrete structure. Will the manual hand compactors work in this case?
PS: I have uploaded a a rough drawing of the structure for your reference.