How many passes a 14 Tonne vibratory roller should make to achieve 100% compaction for base course aggregate? The MDD is 2.315 T/cum, OMC = 7%. Please help as the site is facing serious delays because of less compaction achieved even after 5-6 full passes. The maximum compaction achieved is only 85%!!
Hope somebody can help me out of this anamoly....
Regards
How many passes a 14 Tonne vibratory roller should make to achieve 100% compaction for base course aggregate? The MDD is 2.315 T/cum, OMC = 7%. Please help as the site is facing serious delays because of less compaction achieved even after 5-6 full passes. The maximum compaction achieved is only 85%!!