StrEng007
Structural
- Aug 22, 2014
- 506
Hello everyone,
Any recommendations on applying a baseplate (1 anchor at each corner of a square baseplate, (4) total) with a vertical point load and overturning moment from a column, on an unreinforced slab on grade? My gut reaction is to provide an explicit shallow foundation to resolve this. A major concern of mine is whether or not sawcuts are going to be present in the location of the baseplates. However, for the exercise (ACI 318-14):
1. Check punching shear on the slab (ACI section 14.4.3.4.1)
2. Estimate/iterate a plan area of concrete below the footing to resolve the combined P/A +- M/S:
a. Determine the soil-bearing reaction (iterate for allowable limits).
b. Check tensile flexure in footing, along the compressive soil side, using Mn=5λ√f'c Sm.
c. Check one-way shear in footing, (ACI section 14.4.3.3.1).
d. Resolve overturning tensile side with post-installed anchor bots.
If an explicit shallow foundation/spread footing is provided by saw cutting, removing the slab, and pouring back a reinforced footing, would you dowel the old slab into new footings? This assumes top of slab = top of new spread footing.
Any recommendations on applying a baseplate (1 anchor at each corner of a square baseplate, (4) total) with a vertical point load and overturning moment from a column, on an unreinforced slab on grade? My gut reaction is to provide an explicit shallow foundation to resolve this. A major concern of mine is whether or not sawcuts are going to be present in the location of the baseplates. However, for the exercise (ACI 318-14):
1. Check punching shear on the slab (ACI section 14.4.3.4.1)
2. Estimate/iterate a plan area of concrete below the footing to resolve the combined P/A +- M/S:
a. Determine the soil-bearing reaction (iterate for allowable limits).
b. Check tensile flexure in footing, along the compressive soil side, using Mn=5λ√f'c Sm.
c. Check one-way shear in footing, (ACI section 14.4.3.3.1).
d. Resolve overturning tensile side with post-installed anchor bots.
i. Will the load path at anchor tension warrant a local check of the slab adjacent to the anchor bolts. I'm thinking tension induced from "lifting up" the slab
If an explicit shallow foundation/spread footing is provided by saw cutting, removing the slab, and pouring back a reinforced footing, would you dowel the old slab into new footings? This assumes top of slab = top of new spread footing.