- Mar 28, 2022
- 4
Referencing thread507-119706
My coworker and I were discussing if all cells need to be grouted fully below grade. The reason for the discussion was specifically an elevator pit composed of CMU walls. He enlightened me that all cells in a CMU retaining wall must be grouted full per code, but there is no code provision in the IBC or TMS that I could find that states that.
The only reference I could find was in the IRC 2018 R403.1 "All exterior walls shall be supported on continuous solid or fully grouted masonry or concrete footings..."
Is anyone familiar with a reference to the IBC or TMS requiring fully grouted walls? This is for a commercial building. I understand the logic of it, but it would be great to know the code reference.
My coworker and I were discussing if all cells need to be grouted fully below grade. The reason for the discussion was specifically an elevator pit composed of CMU walls. He enlightened me that all cells in a CMU retaining wall must be grouted full per code, but there is no code provision in the IBC or TMS that I could find that states that.
The only reference I could find was in the IRC 2018 R403.1 "All exterior walls shall be supported on continuous solid or fully grouted masonry or concrete footings..."
Is anyone familiar with a reference to the IBC or TMS requiring fully grouted walls? This is for a commercial building. I understand the logic of it, but it would be great to know the code reference.