solid7
Mechanical
- Jun 7, 2005
- 1,403
I have a project that involves tying a floating slab (approximately 4" thick by 4' X 12') back into the main slab of a home. The main slab is 6-8" thick, and is the foundation of the home. The home is in a beachside community, so it is built on sand. Apparently, the cause of the float was twofold:
1) no initial underpinning and tie-in
2) no gutters on the home
The lack of gutters appears to have caused undermining of the sand around the base of the slab, resulting in a shift in the entire slab. (and a complete break-away from the foundation)
I have already had the slab underpinned, to prevent any further movement in the vertical direction. However, because there had been some repair on the main walls, (this was hurricane damage) it was decided not to pressure grout, so as not to cause damage to the walls or roof. (as the repairs were made in the "sunken" condition)
So my question is: what would be the best way to tie back into the foundation? While the front of the slab is supported, the back half is not, and should, I believe, be tied in properly.
My idea was to put in Z-bent rebar every 12-15", and run it half the depth of the floating slab. Is this sufficient? Or should the slab be also underpinned on the back side? Additionally, there is a 1/4" - to 3/8" gap running the full length of the slab, full depth. Should this be filled with and expansion joint, or a full tie-in repair be made with the existing slab?
thank you in advance.
-----------------------------------------------------------
Catia Design|Catia Design News|Catia V5 blog
1) no initial underpinning and tie-in
2) no gutters on the home
The lack of gutters appears to have caused undermining of the sand around the base of the slab, resulting in a shift in the entire slab. (and a complete break-away from the foundation)
I have already had the slab underpinned, to prevent any further movement in the vertical direction. However, because there had been some repair on the main walls, (this was hurricane damage) it was decided not to pressure grout, so as not to cause damage to the walls or roof. (as the repairs were made in the "sunken" condition)
So my question is: what would be the best way to tie back into the foundation? While the front of the slab is supported, the back half is not, and should, I believe, be tied in properly.
My idea was to put in Z-bent rebar every 12-15", and run it half the depth of the floating slab. Is this sufficient? Or should the slab be also underpinned on the back side? Additionally, there is a 1/4" - to 3/8" gap running the full length of the slab, full depth. Should this be filled with and expansion joint, or a full tie-in repair be made with the existing slab?
thank you in advance.
-----------------------------------------------------------
Catia Design|Catia Design News|Catia V5 blog